Later this week the shoring towers will be disassembled and the panels will be washed and caulked. This will allow the roofing to be repaired and the interior face of the panels to be painted.
Next week you will see additional steel supports added to the north and south elevations to stiffen the existing steel columns.
First Panel being hoisted off of the truck. |
Crane erecting first panel of the day into place. |
Close up of thin brick finish on the precast panels. |
Iron worker installing shims under the panel. |
Progress as the erectors work from the south elevation to the north. |