Monday, August 27, 2012
Cadet Construction Update - Week of August 27, 2012
Student Activities Center - Back To School Edition: The students returned to a much different view from the parking lot today on the first day of school. Last week the east gymnasium floor plank, walls and joists were set in place and site paving was completed in preparation for the start of school. Roofing will begin this week working from the West to the east with the installation of windows starting the first week in September. The building remains on schedule to be enclosed in November.
Thursday, August 16, 2012
Cadet Construction Update - Week of August 13, 2012
Student Activities Center:
Sitework: Site activities are ongoing in preparation for the start of school on August 27th. The first lift of asphalt is complete on the new access road off of Mendota Heights Road. Next week a strip of asphalt will be installed in the plaza between the new building and the stadium to provide access during the athletic season. The parking areas and site fencing are being adjusted to accomodate student and faculty parking. Below is an image of the parking and staging plan:
Building Structure and Enclosure: Exterior precast wall panels continue to be erected along with structural steel. Roofing and exterior window installation will begin in September on gymnasium spaces with the classroom space to follow shortly after. Interior work such as walls, slabs and mechanical rough in will follow the roofing. The building is scheduled to be enclosed by the end of November.
Sitework: Site activities are ongoing in preparation for the start of school on August 27th. The first lift of asphalt is complete on the new access road off of Mendota Heights Road. Next week a strip of asphalt will be installed in the plaza between the new building and the stadium to provide access during the athletic season. The parking areas and site fencing are being adjusted to accomodate student and faculty parking. Below is an image of the parking and staging plan:
Building Structure and Enclosure: Exterior precast wall panels continue to be erected along with structural steel. Roofing and exterior window installation will begin in September on gymnasium spaces with the classroom space to follow shortly after. Interior work such as walls, slabs and mechanical rough in will follow the roofing. The building is scheduled to be enclosed by the end of November.